Education Agency Proposes Time Extension for School Construction

Jakarta Dept. of Education proposes time extension for five out of 38 school construction projects which were using 2016 city budget.

The projects are SDN 06-09 Penjaringan, SDN 11-12 Pejagalan, SMPN 162, 244 and 266

The effort is taken since the projects only reach 90 percent by December 30, 2016.

“The projects are SDN 06-09 Penjaringan, SDN 11-12 Pejagalan, SMPN 162, 244 and 266,” said Sopan Adrianto, agency’s head, Wednesday (12/14).

Construction of SMPN 143 Delayed

Based on the assessment, the project will finish on January 15, 2017. The SDN 15 and 22 Klender, East Jakarta will complete this month.

“The contractor has promised to complete the project by this month,” he added.

The remaining 33 projects of school building in Jakarta will complete before next year.

Linked News
Popular News indeks
  1. Cilandak Drainage Upgraded to Mitigate Flooding

    access_time27-01-2026 remove_red_eye869 personTiyo Surya Sakti
  2. TransJabodetabek Expansion, a Strategic Step to Increase Public Transportation Use

    access_time26-01-2026 remove_red_eye428 personFakhrizal Fakhri
  3. South Jakarta Tackles 38 Dengue Cases to Prevent Outbreak

    access_time02-02-2026 remove_red_eye420 personTiyo Surya Sakti
  4. Jakarta Prepares OMC and 200 Excavators to Prevent Flood

    access_time26-01-2026 remove_red_eye371 personDessy Suciati
  5. Jakarta Showers to Make Way for Partly Cloudy Skies

    access_time30-01-2026 remove_red_eye360 personDessy Suciati
close