Disdik Ajukan Perpanjangan Kontrak Pembangunan 5 Sekolah

Education Agency Proposes Time Extension for School Construction

Jakarta Dept. of Education proposes time extension for five out of 38 school construction projects which were using 2016 city budget.

The projects are SDN 06-09 Penjaringan, SDN 11-12 Pejagalan, SMPN 162, 244 and 266

The effort is taken since the projects only reach 90 percent by December 30, 2016.

“The projects are SDN 06-09 Penjaringan, SDN 11-12 Pejagalan, SMPN 162, 244 and 266,” said Sopan Adrianto, agency’s head, Wednesday (12/14).

Construction of SMPN 143 Delayed

Based on the assessment, the project will finish on January 15, 2017. The SDN 15 and 22 Klender, East Jakarta will complete this month.

“The contractor has promised to complete the project by this month,” he added.

The remaining 33 projects of school building in Jakarta will complete before next year.

Linked News
Popular News indeks
  1. Abdul Muis Building Fire Response Nears Completion, No Fatalities Reported

    access_time08-08-2026 remove_red_eye586 personAldi Geri Lumban Tobing
  2. Jakarta Announces Rp 1 Fare for Transjakarta, MRT, and LRT on August 17

    access_time13-08-2026 remove_red_eye581 personAldi Geri Lumban Tobing
  3. Jakarta Ensures Public Services Stay Operational After Abdul Muis Building Fire

    access_time08-08-2026 remove_red_eye548 personFakhrizal Fakhri
  4. Pramono Urges MUI to Strengthen Synergy in Maintaining Jakarta’s Harmony

    access_time12-08-2026 remove_red_eye538 personDessy Suciati
  5. Jakarta Remains Indonesia's Top Investment Destination

    access_time07-08-2026 remove_red_eye520 personAldi Geri Lumban Tobing